Cube 8 Residences
Devised an innovative design after thoroughly studying several alternatives assisted by extensive analyses, replacing Secant Pile Walls and Barettes in the conforming tender to resist lateral movements by simple retention system yet complying with requirements imposed on the Design & Build Contract, with substantial cost & time savings.
Use of innovative proprietary cantilever construction platform system to build the cantilevered portion of building above Level 24. Use of modular and repetitive structural system reduced typical floor cycle time to only 6 days while achieving an exceptional structural CONQUAS score of 99.7. Extensive use of precast elements, Prefabricated Bathroom Units and system formwork to enhance buildability, constructability,productivity making the construction faster and the